Câu 157: Project Management Professional (PMBOK 6 and 7)

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience. How should the project manager ensure that the client is effectively represented in the daily meetings?

Nội dung câu hỏi

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience. How should the project manager ensure that the client is effectively represented in the daily meetings?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Recommend agile training programs that best suit the client project manager's schedule.
  2. B. Propose a session for essential agile knowledge transfer for the client team to align with the daily meeting goals. — đáp án hiện tại
  3. C. Realign the project to a predictive approach to ensure optimal collaboration between the teams.
  4. D. Provide the client project manager with agile best practice documents and web resources.