Câu 377: Project Management Professional (PMBOK 6 and 7)

The project manager just started leading a project team from which the previous project manager resigned. After a quick evaluation of the project, it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule.…

Nội dung câu hỏi

The project manager just started leading a project team from which the previous project manager resigned. After a quick evaluation of the project, it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Conduct a meeting with the project team to discuss and address the sources of disagreement. — đáp án hiện tại
  2. B. Crash the project timeline to ensure the project is back on schedule.
  3. C. Inform the stakeholders that the project will be delayed due to previous team management.
  4. D. Issue a change request to extend the project schedule based on identified delays.