Câu 140: Project Management Professional (PMBOK 6 and 7)

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week. How should the project manager address this situation?

Nội dung câu hỏi

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week. How should the project manager address this situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Use project reserves to buy new equipment to avoid an impact to the critical path of the project
  2. B. Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer
  3. C. Explore options with the IT department to expedite the necessary repairs based on criticality of the project — đáp án hiện tại
  4. D. Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays