Câu 181: Project Management Professional (PMBOK 6 and 7)

A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay. The project manager does not agree with the costs submitted by the contractor for the m…

Nội dung câu hỏi

A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay. The project manager does not agree with the costs submitted by the contractor for the missing materials. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the project sponsor to allocate more budget to cover the costs
  2. B. Update the procurement management plan and negotiate with the contractor. — đáp án hiện tại
  3. C. Ask the contractor to review the offer and reduce the costs.
  4. D. Update the procurement strategy and negotiate with the contractor