Câu 394: Project Management Professional (PMBOK 6 and 7)

On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project manager realized that some of the key activities were scheduled over the holiday periods in the overseas offices. What should the project manager do next?

Nội dung câu hỏi

On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project manager realized that some of the key activities were scheduled over the holiday periods in the overseas offices. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Update the schedule to reflect the holidays and notify the project sponsor of the delayed completion.
  2. B. Hire additional personnel on a temporary basis to cover the extra workload during the holiday seasons.
  3. C. Request that the offices in overseas locations work overtime to mitigate schedule slippages.
  4. D. Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage. — đáp án hiện tại