A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages. What should the project manager do?

Nội dung câu hỏi

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders
  2. B. Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register
  3. C. Communicate the risk to the steering committee and request a mitigation plan from senior management
  4. D. Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders — đáp án hiện tại