Câu 225: Project Management Professional (PMBOK 6 and 7)

Development team members are located in three different time zones. It is difficult to find a suitable time to hold the daily standup for all team members. What should the project manager do?

Nội dung câu hỏi

Development team members are located in three different time zones. It is difficult to find a suitable time to hold the daily standup for all team members. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Give up the daily standup and replace it with a daily report.
  2. B. Let the team members decide themselves if they want to join the meeting.
  3. C. Encourage frequent, small team meetings with two or three team members. — đáp án hiện tại
  4. D. Require all team members to join the daily standup regardless of the meeting time.