Câu 37: Project Management Professional (PMBOK 6 and 7)

A junior staff member was recently assigned to the team. The new team member tells the project manager that they are confused because they are not familiar with what is expected of them on the project. What should the project manager do to assist the new team member?

Nội dung câu hỏi

A junior staff member was recently assigned to the team. The new team member tells the project manager that they are confused because they are not familiar with what is expected of them on the project. What should the project manager do to assist the new team member?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Advise the new team member to enroll in project management training
  2. B. Instruct the new team member to review the responsible, accountable consult, and inform (RACI) matrix before asking for help
  3. C. Advise the new team member to review the project charter and stakeholder engagement plan
  4. D. Review the resource management plan and provide mentoring to the new team member if necessary — đáp án hiện tại