Câu 365: Project Management Professional (PMBOK 6 and 7)

A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins to identify, evaluate, and categorize the stakeholder relationships to the program. What is the purpose of this process?

Nội dung câu hỏi

A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins to identify, evaluate, and categorize the stakeholder relationships to the program. What is the purpose of this process?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Identify all stakeholders who can positively affect the project
  2. B. Identify all stakeholders who can negatively affect the project.
  3. C. Incorporate the needs of all stakeholders into the communications management plan — đáp án hiện tại
  4. D. Incorporate only primary stakeholders into the communications management plan