Câu 110: Project Management Professional (PMBOK 6 and 7)

A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact on the project outcomes. Wh…

Nội dung câu hỏi

A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact on the project outcomes. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Determine the impact of the risk and prioritize outcomes that do not affect the tax module.
  2. B. Delay developing the indirect tax module until the tax regulation comes into effect.
  3. C. Assess the impact of the risk with an expert and prioritize further outcomes with the client. — đáp án hiện tại
  4. D. Analyze the impact of the risk and discuss with the team to determine how to separate the tax module.