Câu 198: Project Management Professional (PMBOK 6 and 7)

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register. Which project document should the project man…

Nội dung câu hỏi

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register. Which project document should the project manager review in order to determine the reason for this issue?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Requirements traceability matrix
  2. B. Issue log
  3. C. Stakeholder register
  4. D. Stakeholder engagement assessment matrix — đáp án hiện tại