Câu 272: Project Management Professional (PMBOK 6 and 7)

A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board(CCB). What…

Nội dung câu hỏi

A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board(CCB). What should the project manager do now?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Notify the project team about the change request's approval. — đáp án hiện tại
  2. B. Include the new branch of the bridge in the design.
  3. C. Communicate the decision to the stakeholder who requested the change.
  4. D. Evaluate the adjustments to the project management plan.