Câu 407: Project Management Professional (PMBOK 6 and 7)

A company is launching a new product that has to be ready before the summer season begins. After the discovery process, the team realizes that the requirements are very uncertain. What should the project manager do?

Nội dung câu hỏi

A company is launching a new product that has to be ready before the summer season begins. After the discovery process, the team realizes that the requirements are very uncertain. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask to include some business subject matter experts (SMEs) in the team.
  2. B. Register a risk and define a contingency plan to finish the project on time.
  3. C. Assist the team in proposing a minimum viable product (MVP). — đáp án hiện tại
  4. D. Invite stakeholders to discuss project requirements prioritization.