Câu 306: Project Management Professional (PMBOK 6 and 7)

During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level. What should the project…

Nội dung câu hỏi

During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level. What should the project manager do next with this opportunity?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. No more action is required.
  2. B. Share this opportunity with another project.
  3. C. Further monitor the opportunity. — đáp án hiện tại
  4. D. Establish a contingency reserve to support the opportunity.