Câu 205: Project Management Professional (PMBOK 6 and 7)

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already. What should the project manager do to support the team?

Nội dung câu hỏi

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already. What should the project manager do to support the team?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Provide feedback to the team using project performance evaluations. — đáp án hiện tại
  2. B. Include buffer time in the schedule to absorb future delays.
  3. C. Escalate the impact on the schedule to the project sponsor.
  4. D. Create a change request to extend the project's duration and costs.