Câu 193: Project Management Professional (PMBOK 8)

A project manager works for a communications company. The manager of the mobile equipment department is concerned about the current project's activities. According to the current project management plan, the department will need to purchase special equipment, but the cost was not planned. The project sponsor insists t…

Nội dung câu hỏi

A project manager works for a communications company. The manager of the mobile equipment department is concerned about the current project's activities. According to the current project management plan, the department will need to purchase special equipment, but the cost was not planned. The project sponsor insists the project should move forward because customers will be impacted if the equipment is not available. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Use the contingency reserve to fund the equipment cost.
  2. B. Resolve the issue in favor of the department manager to continue the project.
  3. C. Estimate the cost of purchasing the equipment and submit a change request. — đáp án hiện tại
  4. D. Escalate the conflict to the project sponsor.