Câu 174: Project Management Professional (PMBOK 8)

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not…

Nội dung câu hỏi

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time. How should the project manager handle this situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.
  2. B. File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.
  3. C. Remind the contractor to join the meetings and submit their report as this is their commitment. — đáp án hiện tại
  4. D. Compromise with the contractor to only attend the weekly meetings without submitting the reports.