A complex project has a well-established responsibility assignment matrix (RAM). One of the critical stakeholders flagged a task as an issue since it was not accomplished and has been open for a while. What should the project manager do?
Nội dung câu hỏi
A complex project has a well-established responsibility assignment matrix (RAM). One of the critical stakeholders flagged a task as an issue since it was not accomplished and has been open for a while. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Determine a decision-making authority for task accountability.
- B. Identify who owns this task and discuss the situation with them. — đáp án hiện tại
- C. Assign a project team member to complete the open task.
- D. Influence the stakeholder to not flag the task as an issue.