Câu 150: Project Management Professional (PMBOK 8)
An agile team recently finished a product that met stakeholder expectations. However, a subsequent audit revealed that the product does not comply with local regulations. The team lead learns the team focused on the functions of the product and not the regulatory issues. What should the team lead do differently for th…
Nội dung câu hỏi
An agile team recently finished a product that met stakeholder expectations. However, a subsequent audit revealed that the product does not comply with local regulations. The team lead learns the team focused on the functions of the product and not the regulatory issues. What should the team lead do differently for the next project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Remind the project team that they should collect requirements from all stakeholders.
- B. Instruct the product owner to revise the definition of done (DoD) during the sprint review meeting.
- C. Conduct daily meetings to review the functional and nonfunctional requirements.
- D. Coach the team to solicit nonfunctional requirements in addition to functional requirements. — đáp án hiện tại