Câu 3: Project Management Professional (PMBOK 8)

In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a specific machine available in the market. When the machine reached its destination country, it was blocked by customs authorities who restricted the import of this machine model.…

Nội dung câu hỏi

In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a specific machine available in the market. When the machine reached its destination country, it was blocked by customs authorities who restricted the import of this machine model. What should the project manager have done to prevent this from happening?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ensured that the SMEs correctly defined the project scope and the machine model.
  2. B. Ensured the project sponsor provided enough funding to purchase the latest version of the machine.
  3. C. Ensured that regulatory compliance was considered in the quality management plan. — đáp án hiện tại
  4. D. Ensured that the technical team researched and selected the latest model of the machine.