The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered. What should the project manager do?
Nội dung câu hỏi
The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Determine the risks and identify a resolution during the retrospective meeting. — đáp án hiện tại
- B. Inform stakeholders about the delay during project updates.
- C. Discover the gaps in the communications management plan and address them accordingly.
- D. Determine cross-dependencies and plan a spike in the next sprint.