Câu 32: Project Management Professional (PMBOK 8)

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements. How should the project manager plan the delivery of the project?

Nội dung câu hỏi

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements. How should the project manager plan the delivery of the project?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ignore the unclear requirements and focus on the delivery plan of the project.
  2. B. Wait for the requirements to be more clear before any further action is taken on the project.
  3. C. Break down the requirements and prioritize the requirements into iterative work packages. — đáp án hiện tại
  4. D. Escalate the issue of unclear requirements to the management team and wait for final authorization.