Câu 19: Project Management Professional (PMBOK 8)

In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums. What should the project manager do next?

Nội dung câu hỏi

In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed. — đáp án hiện tại
  2. B. Return to using the scrum master as the facilitator for the daily scrums now that the trial period is over.
  3. C. Ask the facilitators who are doing well to continue and recommend that the others stop facilitating.
  4. D. Retrain all team members on daily scrum facilitation to ensure there is consistency in the approach.