Câu 65: Project Management Professional (PMBOK 8)

During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings. How s…

Nội dung câu hỏi

During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings. How should the project manager handle this?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Communicate directly with the director and inform them of the communications management plan
  2. B. Communicate directly with the client stating that any scope changes must go through the project manager
  3. C. Review the stakeholder engagement plan and put in place any existing actions accordingly — đáp án hiện tại
  4. D. Discuss the issues with the project team and let them know that the project manager will handle scope changes