Câu 136: Project Management Professional (PMBOK 8)

A software development team is working on a new reporting application for a client. During iteration planning, the team agrees the functionality requirements of a feature are unclear. The product owner tells the project manager that delays and quality issues are a major concern for the client. What should the project…

Nội dung câu hỏi

A software development team is working on a new reporting application for a client. During iteration planning, the team agrees the functionality requirements of a feature are unclear. The product owner tells the project manager that delays and quality issues are a major concern for the client. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Assign the task of clarifying the feature requirements to the most experienced team member and the product owner.
  2. B. Suggest to the product owner to postpone the development of the feature until the team feels more confident, even if it affects the project timeline.
  3. C. Plan iteration meetings with the client, product owner, and the team to clarify requirements.
  4. D. Facilitate understanding about the feature requirements in a collaborative session with the team and the product owner. — đáp án hiện tại