A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current. Which action should the project manager take?
Nội dung câu hỏi
A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current. Which action should the project manager take?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Assign a dedicated resource to work on the documentation during the project.
- B. Create a specific sprint to deliver the project documentation.
- C. Focus on the documentation after the features are delivered.
- D. Make documentation a standard part of the definition of done (DoD). — đáp án hiện tại