Câu 127: Project Management Professional (PMBOK 8)
A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholde…
Nội dung câu hỏi
A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Add more resources to complete the remaining deliverables early.
- B. Perform several activities in parallel to compress the schedule.
- C. Review and analyze the risks associated with compressing the schedule. — đáp án hiện tại
- D. Prioritize critical activities and skip noncritical activities.
Cộng đồng