Câu 52: Project Management Professional (PMBOK 8)
The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project. If the project continues on the same path, it will consume twice the time and budget planned. What two actions can the project manager take to be more cost effective? (Choose two.)
Nội dung câu hỏi
The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project. If the project continues on the same path, it will consume twice the time and budget planned. What two actions can the project manager take to be more cost effective? (Choose two.)
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Conduct a stakeholder analysis — đáp án hiện tại
- B. Reinforce team communication.
- C. Update the project management plan with the new timeline
- D. Adopt an incremental approach — đáp án hiện tại
- E. Leverage work between team members