Câu 159: Project Management Professional (PMBOK 8)
A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress. What should the project manager do next?
Nội dung câu hỏi
A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress. What should the project manager do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Capture this in the issue log and escalate it to the project sponsor.
- B. Discuss the need to influence this stakeholder with the sponsor.
- C. Meet with the stakeholder to understand what is causing the delays. — đáp án hiện tại
- D. Facilitate a brainstorming session to find potential workarounds.