Câu 170: Project Management Professional (PMBOK 8)
During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics:1,600 rpm (rate-per-minute) -> stops…
Nội dung câu hỏi
During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics:1,600 rpm (rate-per-minute) -> stops working and crashes the system1,500 rpm (rate-per-minute) -> warns of max rate allowed1,400 rpm (rate-per-minute) -> reduces the power and brakes the engineWhich of the following statements is correct?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 1,600 rpm is a project risk,1,500 rpm is an event that triggers a response strategy, and1,400 rpm is a project issue.
- B. 1,600 rpm is a project issue,1,500 rpm is an event that triggers a response strategy, and1,400 rpm is a project risk. — đáp án hiện tại
- C. 1,600 rpm is a project issue,1,500 rpm is a project risk, and1,400 rpm is an event that triggers a response strategy.
- D. 1,600 rpm is an event that triggers a response strategy,1,500 rpm is a project issue, and1,400 rpm is a project risk.