Câu 61: Project Management Professional (PMBOK 8)

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks, which could cause a delay to the schedule. What should the project manager do first?

Nội dung câu hỏi

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks, which could cause a delay to the schedule. What should the project manager do first?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Assign the tasks to another resource, and ask the resource to work double shifts
  2. B. Update the schedule to reflect the project’s changes in duration
  3. C. Ask human resources (HR) for a replacement, and update the risk register
  4. D. Update the resource management plan and resource allocation chart accordingly — đáp án hiện tại