Câu 100: Project Management Professional (PMBOK 8)

A project manager and project team have brought a project back on track after mapping and removing impediments. During the current sprint, the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously. However,…

Nội dung câu hỏi

A project manager and project team have brought a project back on track after mapping and removing impediments. During the current sprint, the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously. However, the tasks are not having the same result with the impediment. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Escalate the issue with an impediment to the project sponsor.
  2. B. Implement the mitigation plans listed in the organizational process assets (OPAs).
  3. C. Use the contingency budget to implement schedule compression.
  4. D. Reassess the issue as part of monitoring and controlling. — đáp án hiện tại