Câu 97: Project Management Professional (PMBOK 8)
A project manager has been assigned to a new agile project with a lot of rapidly changing knowledge areas. How should the project manager manage the knowledge transfers on this project?
Nội dung câu hỏi
A project manager has been assigned to a new agile project with a lot of rapidly changing knowledge areas. How should the project manager manage the knowledge transfers on this project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Mentor the team and stakeholders to ensure domain knowledge is being exchanged properly among them during sprints. — đáp án hiện tại
- B. Work with the quality assurance (QA) team to make sure all domain knowledge is being transferred properly among stakeholders.
- C. Ask the project team to set up the initial sprints to transfer domain knowledge before focusing on the deliverables.
- D. Request the stakeholders to completely document all the domain knowledge before starting the project.