Câu 198: Project Management Professional (PMBOK 8)

A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar prod…

Nội dung câu hỏi

A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar product. What should the project lead do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Work with the product owner to assess the impact and reprioritize the product backlog. — đáp án hiện tại
  2. B. Schedule a meeting with the project sponsor to identify and allocate additional resources.
  3. C. Meet with the scrum master to determine if the development cycle can be reduced.
  4. D. Submit a formal change request and obtain approval from the change control board (CCB).