Câu 82: Project Management Professional (PMBOK 8)

During the execution of an AI project, the different teams responsible for developing deliverables are consistently delayed. The teams do not have access to shared resources or are dependent on other teams to complete tasks. What should the project manager do first?

Nội dung câu hỏi

During the execution of an AI project, the different teams responsible for developing deliverables are consistently delayed. The teams do not have access to shared resources or are dependent on other teams to complete tasks. What should the project manager do first?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Update communication processes to avoid roadblocks.
  2. B. Meet with the team to prioritize goals to avoid impediments.
  3. C. Meet with the teams involved to identify the root cause. — đáp án hiện tại
  4. D. Use project management tools to identify bottlenecks.