A project manager is concerned that the percentage of fixed defects encountered during the testing phase has barely reached the required percentage goal for moving the product to production. What should the project manager do?
Nội dung câu hỏi
A project manager is concerned that the percentage of fixed defects encountered during the testing phase has barely reached the required percentage goal for moving the product to production. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Include additional resources to help decrease the issues found.
- B. Identify the root cause of the issues found through analysis. — đáp án hiện tại
- C. Assure the team that the issues will be addressed at a later stage.
- D. Schedule a lesson learned meeting to understand the issues.