Câu 134: Project Management Professional (PMBOK 8)
An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month. What should the project manager h…
Nội dung câu hỏi
An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month. What should the project manager have done to avoid this scenario?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Requested an experienced resource as a replacement — đáp án hiện tại
- B. Negotiated additional time to complete the project
- C. Allocated additional time for mentoring
- D. Convinced the critical resource to remain on the project