Câu 15: Project Management Professional (PMBOK 8)

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project schedule. When the project manager retu…

Nội dung câu hỏi

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project schedule. When the project manager returns, a detailed schedule is almost complete. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ensure that the schedule is aligned with the vision and objectives. — đáp án hiện tại
  2. B. Escalate the compliance issue to the project management office (PMO).
  3. C. Congratulate the team and move on to the execution phase.
  4. D. Develop a new detailed schedule with the team and project sponsor.