Câu 9: PRINCE2 7 Foundation
When developing a business case, the project manager reviewed the end project report from a previous similar project that stated that costs had been underestimated on the project. Which principle is being applied by the project manager when reviewing this information?
Nội dung câu hỏi
When developing a business case, the project manager reviewed the end project report from a previous similar project that stated that costs had been underestimated on the project. Which principle is being applied by the project manager when reviewing this information?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Learn from experience — đáp án hiện tại
- B. Tailor to suit the project
- C. Manage by stages
- D. Ensure continued business justification
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.