Câu 35: PRINCE2 7 Foundation
Which TWO are objectives or the ‘closing a project’ process?1. To ensure the benefit reviews enable the project benefits to be confirmed2. To update the business case so that the project board can decide whether to continue with the project3. To ensure that the project team deliver the products to quality expectations…
Nội dung câu hỏi
Which TWO are objectives or the ‘closing a project’ process?1. To ensure the benefit reviews enable the project benefits to be confirmed2. To update the business case so that the project board can decide whether to continue with the project3. To ensure that the project team deliver the products to quality expectations4. To hand over any open threats to operations
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4 — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.