Câu 15: PRINCE2 7 Foundation
Which TWO are objectives or the ‘controlling a stage’ process?1. To focus attention on delivering work within the agreed tolerances2. To create follow on action recommendations for all open issues and risks3. To understand how the quality required will be achieved4. Io ensure that the stage s products meet agreed qual…
Nội dung câu hỏi
Which TWO are objectives or the ‘controlling a stage’ process?1. To focus attention on delivering work within the agreed tolerances2. To create follow on action recommendations for all open issues and risks3. To understand how the quality required will be achieved4. Io ensure that the stage s products meet agreed quality expectations
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4 — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.