Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?1. It should be replaced by the project manager attending a daily stand-up.2. It should be displayed in the form of an information radiator in a team room.3. It should be produced when the amount to be delivered…
Nội dung câu hỏi
Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?1. It should be replaced by the project manager attending a daily stand-up.2. It should be displayed in the form of an information radiator in a team room.3. It should be produced when the amount to be delivered will result in tolerance being exceeded.4. It should be produced in a product backlog in the form of prioritized user stories.
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 1 and 2 — đáp án hiện tại
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4