Câu 43: PRINCE2 Foundation

Which of the following statements about the Closing a Project process are true?1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.2. The Closing a Project process provides a fixed point to review if the objectives set out in the…

Nội dung câu hỏi

Which of the following statements about the Closing a Project process are true?1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Only 1 is true
  2. B. Only 2 is true — đáp án hiện tại
  3. C. Both 1 and 2 are true
  4. D. Neither 1 or 2 are true