Câu 57: PRINCE2 Foundation
Which of the following statements about the Project Initiation Documentation are true?1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.2. The Project Initiation Documentation should be updated at the end of each stage to reflect the curre…
Nội dung câu hỏi
Which of the following statements about the Project Initiation Documentation are true?1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Only 1 is true
- B. Only 2 is true
- C. Both 1 and 2 are true — đáp án hiện tại
- D. Neither 1 or 2 are true