CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 32: PRINCE2 Practitioner 6 and 7 Editions

The project is in the ‘initiating a project’ process. The BuildyBrick team manager has now produced more detailed estimates for each of the remaining four stages and advised the project manager of the additional time and cost needed to deliver the project. The project manager needs to use this information to advise th…

Nội dung câu hỏi

The project is in the ‘initiating a project’ process. The BuildyBrick team manager has now produced more detailed estimates for each of the remaining four stages and advised the project manager of the additional time and cost needed to deliver the project. The project manager needs to use this information to advise the project board of the additional cost and whether the project is still justified before requesting project authorization. Which role should be informed about the updated business justification?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Business layer
  2. B. BuildyBrick team manager
  3. C. Project assurance — đáp án hiện tại
  4. D. Project support

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề