Câu 15: PRINCE2 Practitioner 6 and 7 Editions
The project is at the end of stage 1. The project manager is preparing the full business case using the PRINCE2 supporting techniques. The investment appraisal includes an assessment of the value of the underground parking space and potential income. This is based on the net present value of the anticipated income fro…
Nội dung câu hỏi
The project is at the end of stage 1. The project manager is preparing the full business case using the PRINCE2 supporting techniques. The investment appraisal includes an assessment of the value of the underground parking space and potential income. This is based on the net present value of the anticipated income from the car park compared with the estimated cost of construction and offset by any associated risks. As the operating costs for the car park are not yet known, the decision has been taken not to include them. Is this decision an appropriate application of the ‘business case’ practice, and why?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Yes, because business justification should be based on the estimated cost of construction against the anticipated benefits offset by any associated risks
- B. Yes, because the value of future benefits from car park income should be based on the current valve of money calculated using a discount rate
- C. No, because the investment appraisal should include the cost of maintaining the car park as well as the cost of its construction — đáp án hiện tại
- D. No, because the anticipated income from the car park is uncertain and there is a risk that the benefits may not exceed the cost of construction
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.