Câu 23: PRINCE2 Practitioner Edition 6

Which 2 statements apply to either the Development Interfaces or Operations and maintenance interfaces sections?

Nội dung câu hỏi

Which 2 statements apply to either the Development Interfaces or Operations and maintenance interfaces sections?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Delete entry 2 because this interface will be contained in the Communication Management Strategy.
  2. B. Delete entry 3 because this interface will be contained in the project control section of the Project Initiation Documentation.
  3. C. Amend entry 4 to 'The transferred products relating to the services provided by the Facilities Division'.
  4. D. Add 'Project Board, with responsibility for communicating progress to corporate management' to — đáp án hiện tại
  5. E. Operations and maintenance Interfaces.
  6. F. Add 'Facilities Team Manager, with responsibility for the transfer of services provided by the Facilities Division' to Development Interfaces. — đáp án hiện tại