Câu 38: PRINCE2 Practitioner Edition 6

The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not be…

Nội dung câu hỏi

The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.''In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e-learning course' whenever a part of the 'classroom-based training materials' gains accreditation''.Is this appropriate, and why?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Yes, because delivering incrementally will reduce the impact of the threat.
  2. B. Yes, because a risk response needs to be implemented for this major threat.
  3. C. No, because risks responses should be identified as part of the 'plan' step. — đáp án hiện tại
  4. D. No, because a risk action should be allocated to implement a response.