CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 105: PRINCE2 Practitioner Edition 6

The Health and Safety Training Project is closing as planned. According to the contract terms, suppliers must submit all invoices within one week of project closure. The project manager will issue a project closure notification informing all suppliers of this invoicing deadline as part of the 'recommended project clos…

Nội dung câu hỏi

The Health and Safety Training Project is closing as planned. According to the contract terms, suppliers must submit all invoices within one week of project closure. The project manager will issue a project closure notification informing all suppliers of this invoicing deadline as part of the 'recommended project closure' activity. Is this appropriate, and why?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Yes, because the project board should approve the project closure notification drafted by the project manager.
  2. B. Yes, because a project closure notification should be sent to suppliers as part of the 'closing project' process. — đáp án hiện tại
  3. C. No, because the project board should issue a project closure notification as part of the 'directing a project' process.
  4. D. No, because the project manager should notify stakeholders using the approved project closure notification.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề