Câu 28: PRINCE2 Practitioner Edition 6

Which 2 alternative actions apply to the proposed Executive for this project?

Nội dung câu hỏi

Which 2 alternative actions apply to the proposed Executive for this project?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Retain because he accepts that outsourcing is the best solution.
  2. B. Replace with 'Director of Finance Division' because she can ensure a cost-conscious approach to the project that gives value for money. — đáp án hiện tại
  3. C. Retain because he has the right level of authority to be able to control the strategic nature of the Outsourcing project. — đáp án hiện tại
  4. D. Add 'Director of Finance' because she understands the operation of the Information Technology Division and the Facilities Division.
  5. E. Replace with 'Payroll Manager' because he is a very experienced and efficient qualified accountant.